SubscribeThe PID is an essential document for PRINCE2 and for project management in general. It bundles the necessary documents to start the project on a solid basis and is used as a reference point throughout the project. Learn more about the PID (Project Initiation Documentation) and how to write it.
Within a PRINCE2-context the PID (Project Initiation Documentation) is a logical set of documents that brings together the key information needed to start the project on a sound basis and that conveys the information to all involved with the project.
The purpose of the PID is to define the project, in order to form the basis for its management and an assessment of its overall success. The PID gives the direction and scope of the project and (along with the stage plan) forms the “contract” between the project manager and the project board.
The three primary uses of the PID are to:
The PID is a living product which should always reflect the current status, plans and controls of the project. Its component products will need to be updated and baselined again over time, to the necessary extent at the end of each management stage. This is to reflect the current status of its constituent parts.
The version of the PID that was used to gain authorization for the project is preserved as the basis against which performance will later be assessed when closing the project.
The PID is composed of the following parts:
The PID includes the information available in the project brief. Indeed, the project brief describes the purpose, the cost, the deadlines, the performance requirements and the constraints of a project. It is developed before the start of the project during the Starting up a project process and used throughout the Initiating a project process to create the PID and its components. It is then replaced by the PID and is not kept. A project brief includes the following:
These essential elements of the project brief are therefore included in the PID and supplemented with new elements obtained after:
The Project Initiation Documentation consists of almost all the management documents from the Initiation Stage except the Benefits Management Approach as this comes to life after the project and is not archived with the other project documents.
The PID could be:
Are you curious to learn more about PRINCE2 Project Management? Also read: What is PRINCE2?